20A, 20B, 20C – Special provisions for contract relating to infrastructure project, SRA, 1963

20A. Special provisions for contract relating to infrastructure project.-

(1) No injunction shall be granted by a court in a suit under this Act involving a contract relating to an infrastructure project specified in the Schedule, where granting injunction would cause impediment or delay in the progress or completion of such infrastructure project.

Explanation.-For the purposes of this section, section 20B and clause (ha) of section 41, the expression “infrastructure project” means the category of projects and infrastructure Sub-Sectors specified in the Schedule.

(2) The Central Government may, depending upon the requirement for development of infrastructure projects, and if it considers necessary or expedient to do so, by notification in the Official Gazette, amend the Schedule relating to any Category of projects or Infrastructure Sub Sectors.

(3) Every notification issued under this Act by the Central Government shall be laid, as soon as may be after it is issued, before each House of Parliament, while it is in session, for a total period of thirty days which may be comprised in one session or in two or more successive sessions, and if, before the expiry of the session immediately following the session or the successive sessions aforesaid, both Houses agree in making any modification in the notification or both Houses agree that the notification should not be made, the notification shall thereafter have effect only in such modified form or be of no effect, as the case may be; so, however, that such modification or annulment shall be without prejudice to the validity of any anything previously done under that notification.

20B. Special Courts.-The State Government, in consultation with the Chief Justice of the High Court, shall designate, by notification published in the Official Gazette, one or more Civil Courts as Special Courts, within the local limits of the area to exercise jurisdiction and to try a suit under this Act in respect of contracts relating to infrastructure projects.

20C. Expeditious disposal of suits.-Notwithstanding anything contained in the Code of Civil Procedure, 1908 (5 of 1908), a suit filed under the provisions of this Act shall be disposed of by the court within a period of twelve months from the date of service of summons to the defendant:

Provided that the said period may be extended for a further period not exceeding six months in aggregate after recording reasons in writing for such extension by the court